  430 - Deep River Outfall Sewer

PROJECT TYPE

SUB TYPE

LOCATION

OWNER

GEOLOGY

DIMENSIONS
Hand Tunneling Drill and Blast High Point, NC City of High Point Rock 1,400'x82-96" Ø
SUMMARY: This project involved the utilization of two tunneling methods: hand mine drill & blast, and a TBM capable of mining through hard rock conditions. For the most part the 1,000' TBM run was self-supporting, but some of the weaker zones required rock bolts, roof channels, and even liner-plates for a short reach. Two drill and blast road crossings totaling 400' were completed on this job. Both drill... Complete Project Profile